Microsoft withdraws from a UK AI center due to lack of electricity
Microsoft left the contract for an AI data center in Loughton, near London, due to insufficient electrical access. The episode illustrates growing pressure on the UK grid as AI infrastructure projects pile up.
Microsoft has withdrawn from a contract with the British startup Nscale for an artificial intelligence data center in Loughton, Essex, near London. The site was to become the largest AI supercomputer in the UK, but its electrical connection is behind schedule. According to reports, the cause is simple and very unglamorous: the grid does not supply the requested power quickly enough.
A project designed for AI, but stuck by the grid
Announced in September 2025, the project was to host 23,040 Nvidia GB300 graphics processors by the first quarter of 2027 to power Microsoft Azure. Its initial capacity was estimated at 50 megawatts, with a possible extension to 90 megawatts. At this scale, electrical infrastructure is no longer a technical detail; it becomes the deciding factor whether the data center exists or remains on paper.
The blockage comes from access to the UK grid. Nscale was reportedly warned that the site would not receive sufficient power supply before the 2030s, well after the announced opening date. In June, 315 data center projects were already waiting for connection in the UK. In other words, queues no longer concern only banks or airports: they also affect GPU farms.
A signal for AI giants
This withdrawal does not call into question the entire relationship between Microsoft and Nscale, notably in Norway, but it weakens a flagship project of the technological partnership between London and Washington. Microsoft had promised $30 billion investment in the UK between 2025 and 2028, including $15 billion for digital infrastructure. The Loughton contract was among the most visible pieces of this commitment.
For Nscale, the timing is delicate. Financially supported by Nvidia, the British company initiated an IPO process in New York in September, targeting a valuation of about $35 billion. Its prospectus states $103.4 billion in cumulative contracts as of the end of August, but these promises rely on infrastructure delivered on time. In the first half of 2026, Nscale reported about $141 million in revenue, with a net loss close to one billion dollars.
Asked by the Guardian, Nscale says it remains committed to the project and is seeking alternative power supply solutions. The response is cautious, as demand is exploding faster than cables, and cables do not issue press releases.
Key points
- Microsoft leaves the Nscale contract in Loughton, near London.
- The site aimed for 23,040 Nvidia GB300 GPUs by 2027.
- Planned capacity: 50 MW, extendable to 90 MW.
- 315 projects awaited connection in the UK in June.
- Microsoft promised $30 billion to the UK.
- Nscale targets $35 billion valuation in New York.
By the numbers
- 23,040 — Nvidia GB300 GPUs planned at Loughton, according to the September 2025 announcement.
- 50 megawatts — estimated initial electrical capacity of the site, extendable to 90 MW.
- 315 — data center projects awaiting connection in the UK, as of June.
- $30 billion — investment promised by Microsoft in the UK between 2025 and 2028.
- $103.4 billion — cumulative contracts reported by Nscale as of end August 2026.